St. Edward Road Proposal

 

 

FE 346:

Russ Foisy

Eric Forner

Matthew Ghiorse

Bret Macaleer

Jeff Wale

 

 

March 12, 2001

St. Edward State park, Kenmore, Washington

 

 

Table of Contents

         

Objectives           (Matthew, Bret, and Jeff)                        

Site Description (Matthew)

Culvert Design  (Nathan, Jeff)      

Cross Drainage Design (Eric, Bret)

Curve Widening (Russ, Matthew, and Eric)

Haul-time (Jeff, Matthew)

Ballast Design (Nathan Russ)

Clearing and Grubbing (Matthew)

Road Design (Bret)

          Criterion

          RoadEng

Costing (Eric)

 

Objectives

Our main objective for this project was to plot, traverse, stake out and cost a logging road in St Edwards State Park. The primary function of this road is to transport harvested timber from the landing site to a mainline.

 

 

Site Description

Our road site is located in St.Edwards State Park, in Kenmore, Washington. It lies within sections 32 and 33,T.26n,R4E, and sections 4 and 5, T.25N,R.4E, W.M. Each member of the crew team shared all responsibilities. The crewmembers were Nathan Werner, Russ Foisy, Jeff Wale, Matthew Ghiorse, Eric Forner, and Bret Macacleer.

 

 

Culvert Design

Intro/Background

 This crossing is being installed because it is necessary to cross the creek in order to complete the road decided in our FE 346 class.  Due to the fact that there are questions as to whether or not the creek could support fish, the decision was made that the final design must allow for fish passage.

 

 

 

Culvert Design

Process Used in Design of Culvert

The following, is the process and methods used in determining an adequate culvert design. This process should be followed each time a culvert design is undertaken, in order to account for all of the key parameters.

Establish Givens/Assumptions

Side slope ratios

Slope ratios for the culvert design have a direct impact on the length of the culvert. For this reason, we used three different slope lengths in order to aid us in deciding which would offer the most advantageous results. There are no set slope ratios, but according to our specifications we used 2:1 on either side of the curve over the stream.  The steeper the slope the shorter the culvert. The limiting factor here is that as the slope increases, cost increases in order to minimize erosion. Although the 2:1 will erode the least with minimal armament, the length of culvert is considerably longer. On the other hand, if a 1:2 ratio is used, the culvert is much shorter, but the cost to armor the slopes increases due to the need of retaining walls or rock gabions.

Assumed road width

The width of the road was assumed to be 26.2 feet including the curve widening, in order to accommodate our design vehicle.  The point of the crossing occurs at a curve so that a 80 ft. radius was used in coming up with these specifications from the info on curve widening taken from the 2.2 links, Forest Service Handbook 7709.56.  The width of the road will also act as a limitation on the length of the culvert, but cannot be varied.

Assumed height of fill above culvert

The value of 14.5 feet from the flow line was also taken into account to figure the total length of the culvert.  We had to figure the added length do to the 2:1 ratio which added 58 feet to our culvert length.

 

Calculations

Stream gradient

The stream gradient was estimated from the data points and an estimated topographic map produced from Road Eng.  The rise and run were measured in the section of the creek where the culvert will be placed. The rise and run were then divided to calculate a percent slope of 4%.

Length of culvert

The total length of the culvert was figured through means of the road and the side slope ratio and the total came out to equal 84.2 feet.

Discharge values

The discharge values were calculated using the DNR forest practices method.  The Q (discharge) values must be computed for the 100-year event for maximum passage, and the 2-year event for the minimum flow and fish passage needs.

Equations:

 

 

Culvert Dimensions

The dimensions of the culvert were calculated by using the hydraulic charts for the selection of highway culverts prepared by the U.S. Department of Commerce.  The arch culvert dimensions were 58inches by 36 inches.

Depth of water in pipe

The depth of water in the pipe was calculated from the dimensions of the culvert and the flow rate of a 2-year storm. 

Velocity of water in pipe

The velocity of the water in the culvert was calculated using the equation Mannings Equation and then solving for V.  From this we found that our velocity was 7.31 ft/sec which was found assuming the culvert was rectangular for the area that the water reached.  This value was not appropriate for the fish to swim in because the velocity was to great.  Therefore, we then assumed that we would put in some boulders to slow the stream flow and got a knew value of n that equaled .088 found in Environmental Hydrology book on page 223 table 7.5.  From this assumption we then found a knew velocity of 3.16ft/s which did meet the requirements of the fish to move up the stream.

 

Hydraulic Drop

Since the culvert will be layed in at the same grade as the stream bed, there will be no hydraulic drop.

 

 

Fish passage

Species

Although there are many possible fish species that might use Miner Creek, the design fish is the trout that is < 6 inches.

Fish characteristics

The culvert is designed for a trout that is < 6 inches. This is because this fish is the limiting factor; all of the other species can handle greater velocities and have similar needs in terms of depth. This criterion was verified with Ken Bates of the Washington State Fish and Wildlife Department.

Maximum allowable flow velocities and depth requirements

Criteria:

>6-inch adult trout

Adult Pink, Steelhead

Adult Chum Salmon

Adult Chinook, Coho, Sockeye

Culvert Length (ft):

Max. Velocity (ft/s)

Max. Velocity (ft/s)

Max. Velocity (ft/s)

10-60

4.0

5.0

6.0

60-100

4.0

4.0

5.0

100-200

3.0

3.0

4.0

> 200

2.0

2.0

3.0

 

 

 

 

Flow Depth Minimum (ft):

0.8

0.8

1.0

Hydraulic Drop Maximum (ft):

0.8

0.8

1.0


Table from WAC 220-110-070

It is clear that the maximum allowable velocity for the flow in the culvert cannot be greater than 4 ft per second, for culverts between 1 and 200 feet in length. This specific aspect will not allow this design to pass fish because the culvert velocity is 13.8 ft per second.

 

 

 

 

 

 

Cost = 15.48*84.2+29.98*84.2

         = 3827.73

 

 

Cross Drainage Design

Using the following graph for determining cross drain spacing we came up with 3136.64kg per year being a tolerable sediment load and therefore considering our average slope to be about 8% we used the cross-drain spacing of 60 m. 

 

Climate station:

Sappho, WA



Buffer length:

200 m

Soil type:

graveled loam



Buffer gradient:

60 %

 

 

 

Road width:

4 m

Average annual sediment yield (kg)

Road
Gradient

Cross drain spacing

10 m

30 m

60 m

120 m

240 m

2 %

512.64

969.12

1840.36

4097.84

10334.48

4 %

547.88

1136.80

2328.20

5722.04

15737.64

8 %

608.56

1416.36

3136.64

8260.56

24350.16

16 %

702.16

1848.84

4402.52

12162.32

36779.84

Sappho 8 E Snider Ranger Station, WA USA -- August 1999
USFS Rocky Mountain Research Station, Moscow

 

Then using RoadEng we put 18” diameter culverts of various lengths at skew angle of 60 degrees and sloped at –4%.  A total of 10 cross-drains were put in.  The arch for the stream was already put in, but we added it in to our cost calculation

 

The Total cost for the cross-drains was $4678.65

 

 

Culvert length

install cost

Furnish cost

subtotal

30

8.44

8.21

499.5

22

8.44

8.21

366.3

29.5

8.44

8.21

491.17

31.25

8.44

8.21

520.31

23.5

8.44

8.21

391.27

32

8.44

8.21

532.8

20

8.44

8.21

333

39

8.44

8.21

649.35

33

8.44

8.21

549.45

20.75

8.44

8.21

345.48

 total

 

 

4678.65

Stream arch

 

 

3827.73

Grand total                                                      8506.35

 

 

 

 

 

Curve Widening

One of the key elements to designing a low volume road is deciding on what sorts of vehicles are going to be traveling on the road and how often.  There are two main types of vehicles used in the road design. There is the design vehicle, which will use the road the most of any vehicle and should be able to travel the length of the road unassisted. There are the critical vehicles, which will use the road only a few times and may need help through trouble spots, such as filling in the ditch line to make a tight curve.

 

In our road design we have decided that the design vehicle is a standard log truck. Our critical vehicles are a self-propelled yarder and a low boy configuration large enough to bring in a loader.*

 

After the road has been traversed and plotted, it is essential to ensure that all of the vehicles that need to use the road at least once are able to get around the curves. This adjustment is called curve widening.

 

A standard road has a travel width of twelve feet. Due to the length and size of the vehicles, all of them have there own specific traveling width especially around curves. Therefore our first step is to calculate the curve widening needed for each vehicle around each curve. This is done by establishing the radius of the curve, knowing the central angle of the curve and using the specs for the vehicle to attain a length.

 

Standard log truck:

 

L =

 

L1 = wheel base of truck

            L2 = length of stinger

                        L3 = Bunk to bunk distance minus the length of stinger.

 

Low boy configuration:

 

L =  

 

L1 = wheelbase of truck.

L2 = distance from the 5th wheel to the middle of the rear duel wheels for the first trailer.

L3 = distance from the 5th wheel to the middle of the rear duel wheels for the second trailer.

 

* All of the specifications for these vehicles can be found in the attached appendices.

 

 

 

From Figure 1 we can see that L1 is 6m which is 19.685 ft. L2 is 2.6m or 8.531 ft. L3 is 10.5m – 2.6m or 7.9m which is 25.92ft. Therefore

 

            Calculating L for the log truck:

 

L =  

L = 31.408 ft

 

Calculating L for the lowboy:

 

 

L =  

L = 46.25 ft

 

Our first switch back has a radius of 60 ft and a central angle of 180°. Using the curve widening formula found in Forest Service Handbook (FSH) 7709.56, 4.2 – 4.2txt fill.

 

CW =

 

 

Again for the log truck we found

 

CW =

 

CW = 7.4 ft

 

These calculations were done for each curve for the log truck and the lowboy.

 

We found that there are no equation to find the curve widening for our yarder, so we had the use a drafting simulator, which allowed us to represent a scale model of our yarder and our curve. We then traced our yarder along the curve and determined our curve widening for our scale representation.

 

 

Here are our results:

 

Curve

CW for Log Truck (ft)

CW for Low Boy (ft)

CW for Yarder (ft)

R = 60 ft

D = 180°

20.8

39.6

29

R = 70 ft

D = 180°

19.4

26.1

28

R = 75 ft

D = 162.4°

19.4

26.1

27

R = 80 ft

D = 83.6°

19.1

21.6

24

 

R = 120 ft

D = 26.98°

15.07

14.3

22

 

Table 1. Curve Widening Results

 

 

As we discussed our results we concluded that the low boy took precedence over all the other vehicles in all of curves except, our 120 ft radius curve, due to the large amount of curve widening needed.

 

 

 

Taper is needed to integrate our curve onto our road:

 The values we used for each curve are as follows and were determined by Table 2:

 

Curve Radius  (ft):

Taper Length (ft):

60

60

80

50

75

50

70

50

120

30

Table 2: Taper lengths

 

Curve widening tapers should be straight lines before the point of curvature (PC) and after the point of tangency (PT) for the following lengths:

 

Radius (R)(feet) Taper Length (feet)

 

Less than 70                                60

                70-85                           50

                86-100                         40

Greater than 100                                    30

 

 

 

Haul Time

The over all calculations found for haultime were calculated using the computer program Otto Truck Simulator.  In order to use this program the following operations need to be performed. 

 

First the following road information must be obtained and recorded in a tab delimited file from the road eng. map: Distance from beginning of the road to a point at the beginning of a curve for each curve in the road in meters (straight lines are considered a curve with infinite radius), the slope at the beginning of each curve in decimal format, the radius of each curve (straight lines are reported as a 99999 meter curve), the legal speed limit of the road section in km/hr, and the surface type on a 1 to 10 rating (ratings can be found in the Otto Truck Simulator instruction manual).

 

Next the Otto program needs to be opened in DOS and the following information must be inputted into the system: First truck specs are needed including engine and transmission desired (these can be selected from the choices given from the program), and the road file from the previous step must be imported as a ASCII file.  The program will then ask for gear ratios and truck weights (weights will be needed for a loaded and unloaded truck). 

 

Once all this information is inputted the Otto program will try to calculate haultime.  If the transmission does not match the engine type or other problems the program will then inform you and adjustments can be made. 

 

The following data will be supplied by Otto: Distance to the next station, time of travel to the next station, speed between stations, power used, fuel consumption rates, fuel consumed, rpm's, and the gear used between stations.

 

Ballast Design

Our area had 1,000,000 Board feet and was logged in four years.  The things taken into account were trips of vehicles especially loaded log trucks, empty log trucks, yarders and maintenance vehicles. 

 

The Log truck has a capacity of 5,000 board feet and will make approximately 200 trips over 4 years.  The empty log truck will make the same amount of trips and the maintenance vehicle will make approximately 230 trips.  Also, the yarder will make 10 trips.

 

We used a Surface Thickness Program from the Forest Service Department of Agriculture.  Table 1, Table 2, and Table 3 show the steps followed.

 


Table 1.  Traffic Information.  This information was given to us based on usage of the road. 

 


Table 2.  Material Information.  This contains the information on the soil types at the site.  The site had gravel loam and from a compaction chart in ­Earth and Aggregate Surfacing Design Guide for Low Volume Roads from the Forest Service (pg. 32), we figured that it had a CBR of 9.  Our Surface grade is to be high end, so we are using a well graded crushed rock, which has a CBR of 33.


Table 3.  Results.  This takes the input from the first two tables returns calculations here. 

 

From Table 3, we see that there should be a minimum grade thickness of 4.3 inches.  We take this value to be 5 inches and then multiply by 2.  The maximum thickness of a particle is 5 inches and so the ballast thickness should be twice that size giving us a thickness of 10 inches.

 

The total volume of the ballast is 1172.2 cy3 (bases on RoadEng).  The ballast cost is $7.50 per yd3.  The cost to install it is $4.50 per yd3.  This is a total of $12.00 per yd3. 

 

The total cost of the ballast installed is $14,066.40.

 

 

Clearing and Grubbing

Clearing is the process of removing (felling) timber from the right of way

Grubbing is the process of removing stumps/rootwads from the construction area

typically a common cost value for clearing & grubbing is $ 600.-/acre

 

We calculated the total surface area of our road, taking into consideration all the curve widening, and calculated our road is 40,390 sq. ft. This converts to .927 acres. From above we know that it costs $ 600 per acre to clear and grub. This gives us a total of 

 

Clearing and Grubbing: $556.34.

 

 

 

Road Design

Criterion

 

The Technical Use of the Criterion Survey Laser

The laser while developed for timber cruising is very useful as a road survey instrument. It can accurately measure horizontal distance, slope distance, azimuth and percent slope. The laser also gives one the power to store the data in the field; this reduces the human error involved in the relay of data from the instrument operator to the note-taker. This also becomes rather enjoyable when working in wet weather. This however does not mean that the laser is waterproof, it can withstand a rainstorm, but do not throw it in a stream.

 

Equipment Needed To Operate

1.      Criterion Laser

2.      Reflector

3.      Batteries and Cables

4.      Foliage Filter

5.      Shoulder Stock and Strap

6.      A Competent Operator

 

Navigating the Criterion Interface

The criterion data display is limited to only two lines of text.  Designated buttons on the control panel controls the display.  Up, down, and side to side arrows allow the user to scroll through the text.  Options are in folder type arrangement with folders opening up to reveal other folders until a final selection is made.  Once an option is highlighted it can be selected by pressing the 'Enter' button.  The 'Exit' button will take the user back to the previous folder. 

 

Procedure for Criterion 400 (starting a unit survey)

1)      Push the 'POWER' button.  (The word TREE should be displayed)

2)      Use the up and down arrows to Navigate; Go until you find SURVEY and hit 'ENTER'

3)      Then scroll until you find UNIT SURVEY and hit 'ENTER'.  This will be displayed:

*SVY*

(#)

UNIT

(#)

(The asterisks can be moved with the up and down arrows. Choose the numbers that you want to start with preferably 1 and 1.  Each unit number will correspond to a saved unit survey.  The unit # cannot be zero or repeat something that has been saved)

4)      When done use the down key to get to the next menu. (If this does not work push enter then the down arrow)

5)      Scroll down to the screen:

*FROM*

1

TO

2

(This screen indicates the point you are shooting from and the point you are shooting to.  Each shot taken will create a point at the target of the shot.  Your first shot must be a fore shot and will be from point 1 to point 2.  Each side shot also counts as a point.)

6)      Then down arrow until you see:

*FS*  BS

SIDE

USER

 

7)      Make sure that the asterisks are on the FS selection for the initial shot.  If it is not use the left arrow button to select it. 

8)      Push the down arrow to see the following screen:

HD:

FT

AZ:

DEG

(A shot can only be made when the display shows this screen.  Otherwise the criterion will not take a reading.)

9)      Take a reading at eye level to approximately the same height on your partner or tree.  Take first reading to the Left. To do this, push the button on the hand trigger and hold it in. The longer you hold the more accurate reading but shorter the battery life will become.

10)  You have completed your shot and can scroll up or down to view the data that has been collected. 

11)  Scroll until you find:

FS      BS

*SIDE*

USER

 

12)  Push the orange "SIDE" key (which is also the #5 key)

13)  Scroll down to:

HD:

FT

AZ:

DEG

14)  Take a side shot.

15)  Push the orange 'SIDE' key again to take another side shot.

16)  Repeat this process to get as many side shots as you like. 

17)  Scroll up to:

FS      BS

*SIDE*

USER

 

18)  Press the 'INLINE' key.  The asterisks should now be on the BS selection.

19)  Place the criterion over the next point in your road.  (this should be where your fore sight target was placed)

20)  Use the down arrow once to:

HD:

FT

AZ:

DEG

21)  Take your back shot.

22)  Now you are ready to repeat the process.  Make sure that you follow your back shot with a fore shot before shooting side shots.

23)   Go back to step 1

 

Note taking for the Criterion

 

·         Set up your rite in rain notebook like the one shown in Figure 1 below.

·         Begin recording your data at the bottom of the left-hand page and work your way up the page. *

·         Your first shot should always be a foresight.

·         After every Foresight, at least two sides shots should be observed and recorded for data to calculate cross sectional areas. These shot should be taken perpendicular to the road, and one taken in each the downhill and uphill directions. These are the bare minimum required. You should take more shots further away, or at different angles from the point. The flatter the terrain, usually more side shots can be taken to acquire an efficient map of the terrain. All of this information is recorded on the right-hand side of the page. The essential information needed when taking side shots is distance, which gets recorded on the bottom and slope grade, which gets recorded on the top.

·         You then will proceed to the next point and there you take a backsight to the previous point and then another foresight to the next point. Then repeat above.

·         Be sure to leave ample space on the left-hand side of the notebook between foresights and backsights. This allows enough room to on the right hand side of the notebook to record your sideshots and any other pertinent notes that need to be addressed.

          Figure 1: example of field notes

 

 

 

RoadEng

 

Data Transfer

The road data was transferred from an Excel file into RoadEng using the import feature.  The data came into excel in a comma delaminated form.  The FE Handbook describes the following steps for creating a terrain model in RoadEng:

 

Transfer .pol files to RoadEng.

    1. Open Softree 98 then select the Terrain mode.
    2. In the Terrain mode, go to File and select Import
    3. From the small window, select UNIT SURVEY and click on Options.
    4. From the Options window, select the following features and then click on OK.
    5. Softree will take you back to the Import window, click OK.
    6. From the Unit Survey window, find the .pol file that you saved and click on OK.
    7. Softree now creates the plan view of your road.

If the plan view does not resemble the layout of the site that was observed or the plan view seems to be incomplete, the data obtained from the field needs to be rechecked.

    1. To calculate the Terrain model, go to Edit then select Calculate Terrain Model and choose the following features and click on OK. This option from Softree will calculate the contour lines on the Plan view of your road.
    2. A plan view the contour lines is created from the Terrain Calculation option.  You can adjust the contour intervals by going back to Step 8 and changing the contour intervals. After the contour lines are added to your plan view, save the file as a .ter file.

 

Terrain Module

In the Terrain module, errors in the data were fixed.  There were a few areas where obvious mistakes had been made in recording the data.  These areas were adjusted to the location that we predicted them.  During data collection a connecting line was run from the end of the road to a control point on the road.  This line was removed in the Terrain module. The data was transferred from the Terrain module to the Location module.  The following steps were performed as found in the FE Handbook.

 

Transferring data to the Location mode.

    1. From the Edit menu, select Select Feature(s) and click on All.
    2. From the File menu, select Export Feature…and click on Ok.
    3. A Traverse Document Export file window will be shown which allows you to save your file with a .db1 extension.
    4. A warning window may be shown notifying that the side slope extends outside of the Terrain Model. Select OK.
    5. From Module, select to Location screen. From the File menu or the open folder icon, select the .db1 file that you have created. The Survey/Map screen opens the file in a similar format as the Field notebook.
    6. To view the Profile and cross sections of your road, select from the Module menu To Location Design. Select New from the File menu or click on the New icon and a Select P-line traverse window will be shown. Find you .db1 file and click OK.

 

Location Module

                Windows

The majority of the design work was performed within the Location module.  The four windows that were created were the plan, section, profile, and data windows. 

                       

Profile window

In this window the gradeline was adjusted according to the desired slope.  Here adjustments can be made to the vertical location of the road.  Vertical curves were created to smooth the transition between grades.  A mass haul subwindow was created here.  This was adjusted by creating mass haul waste locations. 

 

Plan window

This window shows and overhead view of the road.  Here adjustments can be made to the horizontal location of the road.  Horizontal curves were created to smooth the transition between straight-aways.  This window also shows the road width.

 

Section window

This window shows a cross section view of the road prism.  No adjustments are made here in this view.  It is only for reference. 

 

Data window

This window shows all data sets in tabular format.  The columns can be chosen from the view menu. 

 

            Templates

Road prism templates were created for each curve, straightaway, and taper.  These templates were assigned to the proper road locations.  Here the road width, ballast height, and side slopes were specified. 

 

Culverts

Culverts were inserted into RoadEng using the Edit Culvert function in the Edit menu.  The depth and length were adjusted here to fit each location.

 

Costing

Clearing and Grubbing

 

$556.34

Culverts and Stream Arch

total = $8506.35

 

 

Culverts

$4678.65

 

Stream Arch

$3827.73

Ballast Costs

 

$14,066.40

Haul time costs

 

$811.37

Excavation

 

$31,052.00

Grand Total

 

$54,992.50

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix